How Bernabéu handles multi‑use events: concert staging, potential NFL layout, esports showcases and conversion timing.

Adapt pitch area without permanent compromise; retractable turf system central.
| Phase | Action | Approx Duration |
|---|---|---|
| 1 | Pitch retraction & chamber protection | Hours |
| 2 | Floor panel installation | 0.5–1 day |
| 3 | Stage scaffold & rigging | 1–2 days |
| 4 | Audio/visual calibration | Concurrent |
| 5 | Event | N/A |
| 6 | De‑rig & floor removal | 1 day |
| 7 | Pitch restoration cycle | Controlled re‑emergence |
| Factor | Constraint |
|---|---|
| Weather | Impacts staging safety |
| Scheduling | Tight windows near key fixtures |
| Staffing | Specialized rigging crews |
| Turf Health | Recovery metrics govern next match readiness |
Modularity + data‑driven turf protection empower high event diversity while preserving elite football standards.